5-week total fit-out program in the busy Piccadilly Station, Manchester. Before we could start, we had to gain approvals for H&S from Network Rail. There were very restricted delivery times and certain tasks could only be carried out during the night.
Works Undertaken
- Remove existing and install new shopfront
- New plasterboard partitions walls and mf ceilings
- Flooring
- Installation of display equipment, new staff kitchen and cash desk
- Decorations
- Upgrading of electrics including new 3-phase board and wiring for new lights and emergency lights